![]() You will notice that every task with a Total Slack value of 0 days is shown as a critical task, while every task with a Total Slack value greater than 0 days is shown as a non-critical task. ![]() In Microsoft Project, the critical path is defined as "the series of tasks with 0 days of Total Slack." To see the Total Slack for every task in your project, apply the Schedule table in any task view and then pull the split bar to the far right side of the table to expose the Total Slack column. This means that the critical path can change many times over the life of a project. Every time you make a schedule change in your project, the software recalculates the critical path. ![]() In Microsoft Project, the critical path is dynamic rather than static.